The problem with any approach to estimation

Despite all the times you may have tried, estimating an IT project always seems to be a losing proposition. Why can’t we seem to get it right? I’ve had the opportunity to try my hand at approaches to estimating a number of times, and I believe I’ve come upon one useful insight that any estimating process you define has to take into account – human behavior!

In IT, the majority of costs associated with any project are Iikely to be labor. Numerous strategies exist for trying to get at the “right” amount of labor. You can estimate by proxy, by analogy, top down, bottom up, wideband-delphi… You name it. (For a great resource, check out Steve McConnell’s “Software Estimation: Demystifying the Black Art.”) But I’m going to propose that no typical strategy here will help. The problem isn’t how you arrive at the amount of labor; it’s what happens afterwards.

Across a portfolio of projects, a good estimating process should be unbiased. That is, it should produce estimates which are equally likely to be overestimated as they are under-estimated. It’s true that any single project may experience an estimating error, but so long as the process is well centered, your business partners ought to be able to make reasonable assumptions about likely outcomes.

In one situation I worked on, we developed a simple regression model based on historical data to predict future project estimates. When the model was created using historical data, it performed really well. Even when we selected other random historical projects to test the model, it performed well. Everything would have seemed to indicate that the model was good and wasn’t overfit to the data used to create it.

However, a year after implementing the model, new real world projects that the model had predicted showed a bias towards being under estimated. What was happening? Was our process flawed? Yes and no.

If we were dealing with a process that didn’t involve humans, it’d probably have worked pretty well. However, I’m going to propose that because of humans involved, any estimate created, regardless of the process will have one of two characteristics. Either it’ll be biased towards under estimates or the estimates will be so outrageously large that nobody will want to do business with you. Here’s why…

When you estimate a project you create an effect called anchoring. By stating how much effort the project will take, your teams will align resources on the expectation of that effort. On some days/weeks/months during the life cycle of the project, individuals will be more or less busy. When they are more busy, they will book time equal to the time they worked. However, when they are less busy, because of the resource has been aligned to the project and likely has nothing else to do, they will also book hours to the project. In order to have an unbiased estimate versus actual outcomes, the light times must counterbalance the busy times. However, in order to get paid during the light times, the humans (this is where they mess it all up) still have to book time to your project. Thus, the offsetting light times never come to fruition and the estimate becomes biased towards always being under estimated.

The problem that follows gets even worse. If you use the actual outcomes from these biased results as feedback into your estimate process, it will cause an inflationary effect. Future estimates will be made larger to account for the appearance of under estimating and the process will repeat on subsequent projects. The result will spiral until IT becomes so expensive the business starts looking elsewhere.

It’s grim, but I believe there’s an answer, and it lies in how (frustrating as it may be) the business often treats IT already. Rather than making estimates larger in response to the data, you should adjust your estimating process to make them smaller! I know, this sounds crazy, but hear me out. Let’s say you are finding your projects are 10% under estimated on median. Adjust your process to make estimates smaller, let’s say by 5% and then review the results. If projects are still 10% under estimated, the under estimate you were seeing was likely the result of this waste effect. Continue to shrink your estimates until such time as the under estimating error starts to grow. At this point, you likely have squeezed out the bias caused by light times versus busy times and the under estimates you are now seeing are the result of actually allocating too little effort to the project. Simply undo the shrinking to get you back to your original 10% (or whatever it was) bias, and set your process there. Sure, you’ll always be a little biased towards underestimating projects, but it’s better than an ever bloating IT budget.